内页banner

Case

current position: Home > Case > Case
Installation of dry gas holder piston

Installation of dry gas holder piston

  • Category:Case
  • Browse number:times
  • Release time:2022-12-28 15:42:19
  • Detailed Description

Fabrication and installation construction method of gas holder
1. Prefabrication of gas holder
The wall plates, platforms, side rings on the top of the cover and the hanging rings, bottom rings, upper and lower seals of the movable tower sections are one of the key parts of the gas tank manufacturing and installation process. Their prefabrication quality standards are high, and each construction process is subject to special inspection,
2. Gas holder installation and construction method
The assembly of the bell cover, middle section and water tank wall of the low pressure wet gasometer can be divided into reverse installation method and front installation method.
(1) The inverted installation method is to install the bell jar section by section outward, and finally assemble the sink wall.
(2) The positive installation method is to start from the assembly and welding of the water tank wall and install it section by section to the inside, and finally assemble the bell cover and middle section.

Related products

news.related_news

About

The company is specialized in the construction of gas holder installation, gas holder, gas holder maintenance, gas holder installation, dry gas holder, pipeline and other metal structures.

Service

0516-85858807

Contact

Tel:

177-7822-5566

Email:

MPD@HHAZGS.COM

Address:

No. 160, 2nd Ring West Road, Quanshan District, Xuzhou City


News
support: Sushi