(1) The bottom plate shall be laid in line with the length direction of the plate; Anti-corrosion treatment shall be carried out on the back before laying; The bottom plate shall be welded in sections (blocks) and sections in reverse, and all welds shall be subject to vacuum inspection.
(2) The base column is the framework and walking guide rail of the gas holder, and its spacing is usually 5~7m. During installation, the spacing and the perpendicularity in the radial and tangential directions should be carefully adjusted.
(3) Generally, the bottom oil ditch shall be installed at the corners first and then at the edges. The bottom of the oil ditch shall be close to the foundation. The levelness of the upper plane shall be controlled within 2mm. The surrounding welds shall be subject to tightness test.
(4) The piston installation is generally conducted symmetrically from the center ring outward and the angle oil groove direction at the same time, and the piston plate is used to control the spacing of the piston truss. The welding of piston plate is conducted symmetrically from the central ring outward.
(5) The installation of the cabinet body usually adopts the floating front installation method, which is installed by the mobile small crane or tower crane set on the top of the cabinet.
(6) The weight block shall be configured according to the design requirements and actual weight, and the piston inclination shall be considered.
(7) The sealing device is the key part of sealing gas, which should be installed after the cabinet structure is installed and no welding and gas cutting operations are carried out. The installation sequence is as follows: slide plate assembly, canvas assembly, corner assembly, oil ditch assembly, isolation device assembly, 277 linyi inspection and oil injection.
(8) The piston running test is carried out after the installation and commissioning of the cabinet and sealing device, mainly for the comprehensive assessment of piston tilt, sealing oil system, guide wheel, sealing device, etc.
(9) The walking test is divided into two types: slow speed (generally 1~2 m/rai'n) is used for the full travel rise or fall test, and then the fast fall test is conducted.
The company is specialized in the construction of gas holder installation, gas holder, gas holder maintenance, gas holder installation, dry gas holder, pipeline and other metal structures.
0516-85858807
Tel:
177-7822-5566
Email:
MPD@HHAZGS.COM
Address:
No. 160, 2nd Ring West Road, Quanshan District, Xuzhou City